We develop customized solutions that optimize efficiency and productivity at each stage of manufacturing. With a focus on quality and technology, each project is designed to transform processes and results.

Dash Panel Magna Autotek

Engineering development (design and simulation) of the loading table, double robot manipulator, and modification of the current buffer.

PROCESS

The project for Stellantis consists of the design and simulation of an engineering change, focusing on ensuring precision and efficiency in its implementation. This process includes key activities such as reviewing and defining the layout, analyzing mathematical models, and validating GD&T specifications to define clamping areas.

  • Review and define layout
  • Review and define mathematical models for the project
  • Review GD&T to define clamping areas
  • Create a design draft and present it to the client
  • Modify the design based on client feedback
  • Present design approval
  • Create 2D drawing
  • Finally, present simulation and submit the project

Project Information

The project aims to develop an efficient design and simulation for an engineering change, optimizing key processes and ensuring correct implementation at Magna Autotek within the established timeline and budget.

  • Client

    Stellantis

  • Service

    Design and simulation of engineering change

  • Start date

    October 2024

  • End date

    November 2024

  • Project value

    $826 MDP

  • Implementation location

    Magna Autotek

BIW Platforms KM49 EJ KM74

Mechanical, hydraulic, and electrical installation of manufacturing cells.

PROCESS

This project aims to install and commission key systems in an industrial environment, including the wiring of electrical equipment, the installation of safety systems, and the piping for process lines.

    • Cleaning and securing the area
    • Layout of robots and tooling
    • Installation of fencing or perimeter mesh
    • Installation of cable trays, conduit pipes, and ducting for floors and areas
    • Installation of FRL (Filter-Regulator-Lubricator)
    • Assembly and installation of process piping, water supply, water return, and air
    • Installation of electrical panels and equipment
    • Wiring of 24V communication and power systems
    • Connection to power at PDP 480 and 120 V
    • Installation of safety systems
    • Light curtains, stack light, roll-up door, robot arms, and HMI
    • 24V control wiring
    • Communication wiring
    • Power On

Project Information

The project focuses on the integration of industrial infrastructures, covering the installation of electrical and communication equipment, as well as the implementation of safety and control systems to improve the efficiency and safety of the workspace.

  • Client

    Paslin

  • Service

    Mechanical, hydraulic, and electrical installation of manufacturing cells

  • Start Date

    June 2023

  • End Date

    January 2024

  • Project Value

    $35 MDP

  • Implementation Location

    Magna Autotek, Toluca

BatteryTray-Rivian

Commissioning and programming of Fanuc Robots.

PROCESS

Loading and validation of OLP (offline program), adjustment of UF (User Frame) and UT (User Tool), trajectory validation, collision zone validation, seal and Coherix calibration, DCS configuration, empty test, adjustments to achieve cycle time, automatic run without failures, Burst Build events, BuyOff by FFT and the client.

  • Applications
  • • Material Handling
  • • Spot Weld
  • • Adhesive Application
  • Required Certifications:
  • • DCS

Project Information

The development of programming under the RIVIAN standard. Robot programmers with excellent knowledge and experience in Fanuc robots and the RIVIAN standard, aiming to program 31 Fanuc robots; the commissioning was done at FFT Mexico (Puebla, Puebla) and the final installation at the client’s Rivian plant (Normal, Illinois).

  • Client

    FFT USA / RIVIAN

  • Service

    Robot Commissioning

  • Start Date

    24/10/23

  • End Date

    30/06/24

  • Project Value

    $6 MDP

  • Implementation Location

    Puebla, Puebla / Mexico - Normal, Illinois / USA

PROJECT 4

Pleasure and praising pain was born, and I will give you a complete account of the systems, and expound the actual teachings of the great explorer of the truth, the master-builder of human happiness. No one rejects, dislikes, or avoids pleasure itself, because it is pleasure, but because those who do not know how to pursue pleasure rationally encounter consequences that are extremely painful. Nor again is there anyone who loves or pursues or desires to obtain pain itself.

PROCESS

Complete account of the systems and expound the actual teachings of the great explorer of the truth, the master-builder of human happiness. No one rejects, dislikes, or avoids pleasure itself, because it is pleasure, but because those who do not know how to pursue pleasure rationally encounter painful consequences. Anyone who loves or pursues.

  • Engine oil level should be regularly checked. Tires must have a minimum of 1.6mm of tread.
  • Ensure that the electrolyte level is correct. Never remove the radiator when the engine is hot.
  • Ensure that your vehicle's brake fluid is full. Engine oil level should be regularly checked.
  • Engine oil level should be regularly checked. Tires must have a minimum of 1.6mm of tread.
  • Ensure that the electrolyte level is correct. Never remove the radiator when the engine is hot.

Project Information

Pleasure and praising pain was born, and I will give you a complete account of the systems and the actual teachings of the great explorer.

  • Client

    Indu Designers

  • Category

    Industrial

  • Start Date

    28th Dec 2019

  • End Date

    28th Feb 2020

  • Project Value

    $1250.00

  • Location

    New York City, USA